Water rationing in Panacan WSS extended ‘til Sept 20

DAVAO Water District advises that the ongoing rotational water schedule implemented in Panacan Water Supply System (WSS) is extended until September 20, 2021.

This after the rehabilitation work on Panacan Production Well No. 4, initially targeted to be completed on September 16, 2021, was extended due to bad weather conditions affecting the conduct of several rehabilitation activities.

Once rehabilitation work is completed, DCWD targets to improve its water yield, thus also increasing the available water supply for Panacan WSS.

It can be recalled that DCWD had to shut off the operation of Panacan Production Well No. 4 on August 28, 2021 to carry out rehabilitation work, thus reducing the available water supply for Panacan WSS.

To equitably distribute the remaining water supply, DCWD had to result to the rotational water schedule while the rehabilitation work is ongoing. DCWD is also augmenting water supply in some areas in Panacan WSS through regular water deliveries.

Customers are advised to continue storing water in clean and covered containers during their schedule of water supply availability to prepare for their no water schedule and possible emergency water service interruption.

Following is the schedule of water supply availability:

Area 1

Tibungco (from corner Eliong Road) to Bunawan areas: anytime between 6 to 9 a.m. of Sept. 15 until 6 a.m. of Sept. 16 and anytime between 6 to 9 a.m. of Sept. 18 until 6 a.m. of Sept. 19

Bunawan to Lasang Proper areas: anytime between 9:00 AM to 12:00 NN of Sept. 15 until 6:00 AM of Sept. 16 and anytime between 9:00 AM to 12:00 NN of Sept. 18 until 6:00 AM of Sept. 19.

Lasang Bucana areas: anytime between 12 nn to 3 p.m. of Sept. 15 until 6 a.m. of Sept. 16 and anytime between 12 nn to 3 p.m. of Sept. 18 until 6 a.m. of Sept. 19.

Area 2

Tibungco areas (Davao-Agusan Road, Eliong Road, Cal Vill., Calvo Vill., Tibungco Public Market, and Manggahan Vill.): anytime between 6 to 9 a.m. of Sept. 13 until 6 a.m. of Sept. 15, anytime between 6 to 9 a.m. of Sept. 16 until 6 a.m. of Sept. 18, and anytime between 6 to 9 a.m. of Sept. 19 until 6 a.m. of Sept. 20.

Ilang areas (Davao-Agusan Road, Upper Ilang, Amparo Vill., Bugac Ilang, Central Ilang, and Riverside Ilang): anytime between 9 a.m. to 12 nn of Sept. 13 until 6 a.m. of Sept. 15, anytime between 9 a.m. to 12 nn of Sept. 16 until 6 a.m. of Sept. 18, and anytime between 9 a.m. to 12 nn of Sept. 19 until 6 a.m. of Sept. 20.

Panacan areas (Davao-Agusan Road, Luzville Subd., Sarmiento Subd., Malagamot Areas, MALUPIHA Vill., Muslim Vill., Panacan Valley, Pizzaro Vill., Doña Mercedes Vill., Benjamin Hills, San Miguel Vill., Sunrise Vill., St. Michael Vill., Celedoña Vill., PMPC Vill., Don Ramon Vill., Veteran’s Vill., Panacan Avenue, Panacan Public Market, and Km. 13 Panacan): anytime between 12nn to 5 p.m. of Sept. 13 until 6 a.m. of Sept. 15, anytime between 12nn to 5 p.m. of Sept. 16 until 6 a.m. of Sept. 18, and anytime between 12nn to 5 p.m. of Sept. 19 until 6 a.m. of Sept. 20

Panacan Relocation and Sasa areas (Doña Caridad Subd., De Guzman Vill., PDRHAI Vill., Km.12 Sasa, Bayview Vill., Doña Socorro Vill., San Jose Vill., Landmark Vill. II, Nelia Ville Subd., Cabayugan 1, 2, & 3, San Vicente Vill., BAT Compound, San Lorenzo Ruiz Vill., Airview Heights, SUHA Vill., Doña Mercedes Vill., Mahayahay Settlers, San Antonio Vill., and; Plainview Vill.): anytime between 5 to 9 p.m. of Sept. 13 until 6 a.m. of Sept. 15, anytime between

5 to 9 p.m. of Sept. 16 until 6 a.m. of Sept. 18, and anytime between 5 to 9 p.m. of Sept. 19 until 6 a.m. of Sept. 20.

The DCWD management apologizes to all affected customers and asks for their understanding and cooperation. For any concerns and queries, please contact DCWD’s 24-hour hotlines 244-6767, 0927-798-8966, 0908-441-0653, and 0925-511-3293 and chat support at DCWD’s Facebook Page (www.facebook.com/officialDCWD) and DCWD’s website (www.davao-water.gov.ph). /

The rehabilitation work on Panacan Production Well No. 4, initially targeted to be completed on September 16, 2021, was extended due to bad weather conditions affecting the conduct of several rehabilitation activities.